Summer 2019 Construction

Columbus Elementary

  • Site lighting
  • Roof fan installation
  • Electrical panel upgrades
  • Fire alarm upgrades
  • Student bathroom upgrades
  • Ceiling, lighting and floors in  select classrooms and hallways
  • Door and window replacements
  • Masonry repairs

Westlake High School

  • Boiler replacements
  • Classroom unit ventilators
  • 12 bathroom renovations
  • HVAC upgrades in gym,  auditorium and main office
  • Roof replacement
  • Electrical service and panel upgrades
  • Fire alarm upgrades
  • Ceiling, lighting and floors in select classrooms
  • Door and wire-glass replacements
  • Asbestos abatement in floors and ceilings in guidance office
  • Masonry repairs
  • Site work - sidewalks and parking areas

Overview of Bond-Funded Construction

October 2016  

$39.6 million Facilities Bond Approved

Work Completed as of August 2018

Summer 2017

Westlake High School:  

  • Auditorium Roof Replaced

Westlake Middle School:  

  • Entire Roof Replaced

Summer 2018

Westlake High School:

  • Floors abated and replaced in 41 rooms

Columbus Elementary:

  • Sitework:
    • Road Reconfiguration
    • Parking Reconfiguration
    • Drop-off Circle added
    • Retaining wall
    • Sidewalks
    • Athletic Fields
  • Mechanical Upgrades:
    • Rooftop Exhaust Fans
    • HVAC Controls
    • Library AC
Bond timeline of projects