2016 and 2019 Bond Updates
Summer 2019 Construction
Columbus Elementary
- Site lighting
- Roof fan installation
- Electrical panel upgrades
- Fire alarm upgrades
- Student bathroom upgrades
- Ceiling, lighting and floors in select classrooms and hallways
- Door and window replacements
- Masonry repairs
Westlake High School
- Boiler replacements
- Classroom unit ventilators
- 12 bathroom renovations
- HVAC upgrades in gym, auditorium and main office
- Roof replacement
- Electrical service and panel upgrades
- Fire alarm upgrades
- Ceiling, lighting and floors in select classrooms
- Door and wire-glass replacements
- Asbestos abatement in floors and ceilings in guidance office
- Masonry repairs
- Site work - sidewalks and parking areas
Overview of Bond-Funded Construction
October 2016
$39.6 million Facilities Bond Approved
Work Completed as of August 2018
Summer 2017
Westlake High School:
- Auditorium Roof Replaced
Westlake Middle School:
- Entire Roof Replaced
Summer 2018
Westlake High School:
- Floors abated and replaced in 41 rooms
Columbus Elementary:
- Sitework:
- Road Reconfiguration
- Parking Reconfiguration
- Drop-off Circle added
- Retaining wall
- Sidewalks
- Athletic Fields
- Mechanical Upgrades:
- Rooftop Exhaust Fans
- HVAC Controls
- Library AC